Talk Back
Post a CommentHousingZone Most Popular Stories
- A smaller home can still be beautiful
- Tapping an Overlooked Homebuying Market: Single Women
- 10 keys to a more streamlined homebuilding company
- Retool your sales process to meet tougher mortgage guidelines
- Presenting the 50+ Housing Awards of 2008
- The Land Dilemma: Is it Time to Buy or Sell?
- Here are the 100 Best New Products
- Minimalist Modern House Showcases Art and Architecture
- Modular and Green
- Wood vs. Engineered Lumber
Cash Flow Analysis
A sidebar to 'Project Spotlight: Too Close for Comfort'
May 6, 1999
Professional Remodeler
Ordinarily, Rick Duval collects a hefty down payment and generous progress payments tied to completion of strategic production phases during the job. "We try to set these things so we have a payment every month," he says. The financial plan for the Springer addition was based, Duval says, on a down payment of $15,000 in June, a progress payment of $12,000 at drywall completion in July, another $12,000 due after the tile floor was laid in August and a smaller, final payment due at project completion.
| Budget History |
"We usually have a weekly cash flow report on each job," Duval says. "It’s unusual to have negative cash flow." But when the cash flow is negative, "a red flag goes up." Duval then asks: Is there anything we can do to turn the problem around? The solution would have been to get the drywall on quicker, Duval says. But that was not possible.
As soon as the drywall was done in early August, Duval’s cash flow on the project bounced back to a positive $3,883. A delay in tile installation pushed the next progress payment into late September. The final $4,780 arrived three months after the project had been finished, when the Springers settled a dispute with the HVAC subcontractor over carpet damage. "It wasn’t good for cash flow to wait for that," says Duval.
The weight of production problems sank profits on the Springer job. Duval had expected job costs to come in at $30,600. The drywall and tile installation delays plus other snags -- including changes in the roof design and an unbudgeted cost for in-floor heating prep -- drove costs to $32,753. After accounting for overhead, Duval was chagrined to see that net profit had bottomed out at a negative 1.4 percent.